The Ameenee Magu road project has come to a standstill due to intense rainfall. We advise all citizens using this road to steer clear of the work site as it is currently unsafe for walking.
Day 3: Our team is working around the clock to ensure the timely completion of segments 12 and 13 of the Malé Ameenee Magu Streetscaping project.
#Hafthaa14
#TeamRDC
At Ameenee Magu, the asphalt laying and compaction are complete, while sidewalk paving is in progress. Additionally, ongoing tasks include managing asphalt dust and cleaning the road.
#Hafthaa14
#TeamRDC
I am delighted to have been given the opportunity by Kulhudhuffushi RDC staff to hoist the National Flag at the Kulhudhuffushi RDC Site. Thank you for this honor!
#TeamRDC
Current ongoing work at Ameenee Magu involves ABC laying and compacting.
Completion of Ameenee Magu is a key presidential pledge under development of Malé City roads as a part of
#Hafthaa14
Road Map
#TeamRDC
Tonight's planned tasks at Ameenee Magu include excavating and installing stormwater tanks and pipes, as well as the installation of an HV line. Additionally, there is scheduled work for excavating and installing a dewatering line.
#Hafthaa14
#TeamRDC
Today's additional tasks ongoing includes excavating and installing a stormwater line, as well as excavating and installing a dewatering line and tanks.
#Hafthaa14
#TeamRDC
Work in progress includes the installation of the MWSC sewer pumping line, excavation, and setting up the 160mm house connection sewer line. Additionally, we are removing zigzag blocks and relocating trees.
#Hafthaa14
Presently, the work being carried out at Ameenee Magu includes excavating and installing a dewatering line with tanks, as well as excavating and installing curbstone.
#Hafthaa14
#TeamRDC
Work of Segment 12,13 of Malé Ameenee Magu Streetscaping Project resumed this morning will proceed 24/7.
Current work ongoing includes excavating and connection of MWSC pumping line to adjacent roads.
#Hafthaa14
Installed four line connections near Ministry Junction for the MWSC sewer pumping line. Currently excavating and installing a 160mm house connection sewer line, a 160mm house connection water line, cable trays and pipes, as well as an HV junction and pipe.
#Hafthaa14
The ABC layer is currently being laid at Ameenee Magu segments 12 & 13, and the work is progressing according to the schedule without any delays.
#Hafthaa14
#TeamRDC
The most recent work update involves excavating and installing a 200mm sewer main line. The work has been planned to ensure minimal interruptions.
#Hafthaa14
#TeamRDC
At Ameenee Magu, the ongoing tasks include excavating and installing sewer outfall lines, placing curbstones, and working on the installation of Ooredhoo and HV pipelines.
#Hafthaa14
#TeamRDC
Day 11, Ameenee Magu: The latest project updates include the excavation and installation of the stormwater line, excavating and installing a 400mm sewer outfall line, and the installation of curbstone.
#Hafthaa14
#TeamRDC
Meeting the Kulhudhuffushi City Council was truly an honor. I am confident that, with your cooperation, we can smoothly proceed with the island's road project, minimizing any challenges along the way.
#TeamRDC
Ongoing tasks at Ameenee Magu Project encompass the excavation and installation of a stormwater line, the excavation and installation of a stormwater outfall pipe, and the excavation and installation of curbstone.
#Hafthaa14
#TeamRDC
Malé Ameenee Magu Streetscaping Project is advancing as we excavate and set up the stormwater line, including the butt-welding of a 160mm water pipe.
#Hafthaa14
#TeamRDC
The government aims to resume all projects that were previously halted due to various circumstances. Henceforth, we have recommenced the following road development projects.
#Hafthaa14
Today, during our meeting with Th. Thimarafushi Council, we deliberated on potential solutions to address concerns regarding the delay in the road development project of the island.
The present work at Ameenee Magu includes the installation of curbstone, subgrade leveling and compacting, and the paving of sidewalks.
#Hafthaa14
#TeamRDC
Minister
@muththo
and his team inspected the Ameenee Magu project site to oversee the latest progress and ensure that the projects are on schedule.
#Hafthaa14
Day 8, Ameenee Magu: Excavation and installation of sewer overflow, MWSC water line pressure testing, and the installation of curbstone and 315mm sewer pumping outfall pipes with butt-welding work
#Hafthaa14
#TeamRDC
Engaging with Island Councils is a pleasure, and today, discussions were held with the councils of R. Inguraidhoo and R. Alifushi regarding the road development projects of both islands.
The ongoing tasks at Ameenee Magu comprise excavating and installing the stormwater main line, establishing the stormwater line, installing sewer and water house connection lines, casting valve chambers, and placing curbstones.
#Hafthaa14
#TeamRDC
Reflecting on the tragic period of the Tsunami that claimed the lives of many Maldivians, today we stand together as a nation to honor and remember all those affected. Wishing all fellow Maldivians a Happy Unity Day.
We discussed the constraints in the project, identified solutions, and are optimistic about ensuring a smooth execution moving forward. Thank you HA. Dhidhdhoo Council.
Day 16, Ameenee Magu: Digging and laying the stormwater main line, setting up cable trays and pipes, and installing the water house connection pipe.
#Hafthaa14
#TeamRDC
As we bid farewell to 2023, let's pray to the Almighty for a more promising 2024. Let's include our brothers and sisters in Palestine in our thoughts, wishing for a year of peace ahead.
At Ameenee Magu presently, we are in the process of excavating and installing the sewer outfall line, along with the installation of curbstone.
#Hafthaa14
#TeamRDC
Fishermen play a vital role in fostering nationwide economic growth. They are the guardians of our seas, working diligently to safeguard them. Happy Fishermen’s Day!
I am delighted to have met with the Council and discussed the road development project. Thank you, Sh. Milandhoo Council, for the valuable discussion and collaboration.
I am honoured to meet HA. Filladhoo Council members today and I am confident that we can work together to make the road development project of Filladhoo, a success.